What does indirect labor refer to in the context of project work?

Prepare for the AACE Certified Cost Technician Exam. Benefit from personalized flashcards and multiple-choice questions with detailed explanations. Ensure exam success with our comprehensive study resources!

Indirect labor refers to the labor needed for activities that do not contribute directly to the final installation or outcome of a project, but are necessary for the overall completion of that project. This may include roles such as site supervisors, project managers, and administrative personnel who facilitate the project but do not directly create or alter the finished product.

In project management and cost estimating, it's important to distinguish between direct labor—labor that can be directly tied to the creation of a product or service—and indirect labor, which supports the project in a way that is essential yet not directly observable in the output.

Choosing this answer highlights a fundamental aspect of labor classification in project management: recognizing that not all work on a project is directly related to the main tasks leading to the final deliverable, but still plays a crucial role in making sure that the project runs smoothly and meets its objectives.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy